Loading...

PROJECT DETAILS

Public Realm Works at Liffey Street Upper and Lower in Dublin City Centre.

3,800m2 of Public Realm-Streetscape Works including Major Services Upgrade.

Overview

This project entailed the complete upgrade, modernization and renewal of all utility services, street surfaces, landscaping and street furniture at this prestigious prominent part of Dublin City Centre. Liffey Street measuring 300m, is bordered to the north by Henry Street and to the south by the Ha'penny Bridge. Abbey Street, incorporating the live Luas line, traverses Liffey Street. The works required close liaison and effective communications with all adjacent business including blue chip brand names such as Marks & Spencer, Arnotts, and the likes thereof.

To avoid inconveniencing shopkeepers, businesses, 60,000 daily pedestrians, 120 delivery trucks, emergency services the works were planned and executed on a phased basis. Initially, Jan 2023, we started works on Upper Liffey Street. The street measures 150m in length and was executed employing 20 intricately planned separate phases. Liffey Street South was also successfully delivered employing 24 separate phases as well. Liffey Street South is traversed by Strand Street.

Preparation

Initial preparatory works involved; detailed dilapidation survey of all properties both internally and externally, letter drop to all affected stakeholders, initial contact with all utility providers, erection of four VMS digital board. To guarantee effective communications with all interested parties, we allocated a full time Liaison Officer to the project. Additionally, and to guarantee the effectiveness and safety of our traffic, pedestrian and phasing management initiatives, once erected, we monitored their effectiveness over a two days period before executing works. Every work activity was supported by a Risk Assessment and Method Statement and once approval was obtained all site and plant operatives were activity inducted. Additionally each gang was supported by a Safety Representative and our full time site based H&S Officer conducted daily HSEQ audits. To deal with the large number of services encountered we allocated a full time services coordinator to the project. Hence, all utility providers were provided with 6 weeks notice before any of their works was altered or reconnected. Their representatives were present for all of the most challenging reconnection works. For example, Bord Gais and The ESB were present for all reconnection works.

Key site activities included initial civil engineering works involving; live gas main diversions to facilitate construction of structured tree pits, 300m of a 180mm dia HDPE water main, 150m of a high pressure 320mm HDPE water main, 1,600m of new utility ducting for ESB, Eir, Virgin Media, Public Lighting including new chambers, 300m of 450mm dia surface water drain including 15 new manholes and 25 gullies. At Liffey Street Lower, we encountered 50m3 of contaminated soil that was carefully tested, verified, excavated and exported by Enva Licensed Waste Management company.

As new utility services were laid we also renewed all live connections to adjacent properties without disrupting supplies. In more challenging situations, and to guarantee continued supplies, the transfers were carried out in out of hours. Throughout the works we encountered redundant basements. Once exposed, our structural engineer checked them for structural robustness. Thereafter we cleaned them out (under architect supervision) and then, under instruction, filled them with concrete.

Streetscape Works

New streetscape works followed on from the civils works. Streetscape works involved 3,800m2 of new Iberian and Irish granite kerbs, paving setts and slabs, all laid to patterned falls into formed drainage channels. To cater for heavy delivery trucks the new streetscape works were all laid to a full Dublin City Council road construction specification.

As part of the works, we provided new SUDS tree pits planted with semi mature trees and herbaceous plants and grasses, bespoke seating, custom designed Lighting Columns and Bicycle parking. New controlled and uncontrolled pedestrian crossings at Middle Abbey St & Bachelors Walks were built as part of the scheme.

Challenges

During the works we encountered numerous challenges and all of them were catered for and effectively managed using the following strategies.

CHALLENGE IMPLEMENTED SOLUTION
Effective communications with affected stakeholders. Appointment of a full time Liaison Officer.
Timely letter drop to all stakeholders.
Ongoing communications with fortnightly newsletter emailed.
Nuisance Management - Noise, Dust, Vibrations Designated cutting areas with acoustic shield blankets. Wetting down during dry spells and saw cutting, noise barriers.
Maintaining Utility Supplies Early and timely engagement with utility providers. Out of hours work.
Identifying, protecting and upgrading utility services We allocated a full time services coordinator to the project. Timely contact with all utility providers. Initial CCTV and GPR surveys. Hand excavation in more sensitive areas. All excavators accompanied by a banksman.
Maintaining Luas Operation Close liaison with Luas and carefully planned night time work.
Site Security CCTV and Time Lapse cameras
Recycling

All existing hard surfaces including existing kerbs/paving were all carefully excavated and exported to licensed recycling facilities or recycled to DCC depot The project was planned and supported by a Communications Plan, Works Programme, H&S Plan, QA Plan and a Waste & Environmental Management Plan. Both progress and safety on the project was also monitored in real time by the use of CCTV cameras.

All deep excavations for the drainage, services and the basements were supervised by An Archaeologist. Liffey Street Lower contains Mature London Planes Trees and all works in that area was supervised by an Arborist. The project was finished on time and within budget in accordance with agreed variations. Quality Assurance was achieved throughout.